Development Manager’s Update – June 2023

Welcome to June 2023 update! 

SIGV Release 5

As we head into winter, the site looks a lot different to last month.  

Clearing of the development footprint is almost complete.  Fallen timber has been turned into mulch, some of which will be used on site.  All hollow bearing trees that have been felled have been retained on site and repositioned in the conservation areas to provide additional habitat for fauna.  

Civil works have also started to progress. On the eastern side of the site, the delivery team has commenced construction of the sewer after a successful pre-start meeting with Shoalhaven Water.  On the western side of the site, earthworks have begun under geotechnical supervision.  

Hopefully the good weather continues!

Precinct: Jacob's Range
Stage: Release 5
Expected Registration: Q2 2024

Development Approval (DA)
Subdivision Work Certificate (SWC)
Construction at 25%
Construction at 50%
Construction at 75%
Practical Completion
Subdivision Certificate (SC)
Registration

SIGV Release 5

We look forward to providing you with another update next month. See you then! 

> BACK