Welcome to November 2023 update!
There is nothing like freshly installed kerb and gutter on a land subdivision to really give it the feel that things are coming together – and that is exactly where we are now up to at Sussex Inlet Release 5. With bulk earthworks, pavement boxing, sewer reticulation and drainage now all but completed, the delivery team on the ground has made some serious visual progress to the site. The road sub-base is more than halfway complete. Once the kerb and gutter and sub-base are complete, the team will shift move on to asphalting the roads. Electrical work has also started and is progressing well, being approximately 25% complete.
We look forward to providing you with another update next month. See you then!