Development Manager’s Update – September 2022

Welcome to the  September 2022 update!

SIGV Release 5

Our consultants continue to negotiate the subdivision works certificate (SWC) approval process with revised environmental reports and additional information provided to resolve several requests from Council. We are hopeful that the much-anticipated certificate will be released to allow construction to commence shortly.  

In the meantime, we are putting together a delivery team to construct this stage. Our preferred civil contractor has submitted a cost to complete the construction works and are revving up to get started. The next step is to enter into a construction contract, so we are ready to go once the SWC is received.  

Precinct: Jacob's Range
Stage: Release 5
Expected Registration: March 2023

Development Approval (DA)
Subdivision Work Certificate (SWC)
Construction at 25%
Construction at 50%
Construction at 75%
Practical Completion
Subdivision Certificate (SC)
Registration

SIGV Release 5

> BACK